Construction Timeline Calculator

units
units/day
days/week
weeks

How to Calculate Construction Timeline

To calculate the construction timeline, use the formula:
Timeline (weeks) = Total Workload ÷ (Daily Productivity × Number of Workers × Working Days per Week)

  • Total Workload: The total amount of work (square feet or units).
  • Daily Productivity: The average work completed by one worker in a day.
  • Number of Workers: The total number of workers involved in the project.
  • Working Days per Week: The number of days the team works in a week.

Example

You are managing a construction project to build 10,000 square feet of housing units. Each worker can complete 100 square feet daily. There are 15 workers available, and they work 6 days a week.

  • Total Workload = 10,000 square feet
  • Daily Productivity = 100 square feet
  • Number of Workers = 15
  • Working Days per Week = 6

Timeline (weeks) = 10,000 ÷ (100 × 15 × 6)
Timeline (weeks) = 10,000 ÷ 9,000
Timeline (weeks) ≈ 1.11 weeks

Result:
The project will take approximately 1.11 weeks (about 8 days) to complete.