Labor Cost Calculator
USD/hour
USD
USD
How to Calculate Labor Costs
The formula to calculate total labor costs is:
Labor Cost = (Hourly Rate × Hours Worked × Number of Workers × Days Worked) + Additional Costs
Where:
- Hourly Rate: The wage paid per hour for each worker.
- Hours Worked: The number of hours worked per day.
- Number of Workers: Total employees contributing to the project.
- Days Worked: The duration of work in days.
- Additional Costs: Any extra costs such as taxes, overtime, or supplies.
Example:
A construction project employs 5 workers who each earn $25/hour. They work 8 hours/day for 10 days. Additional costs, such as equipment rental, total $500.
Calculation:
- Hourly Rate = $25
- Workers = 5
- Hours/Day = 8
- Days = 10
- Additional Costs = $500
Using the formula:
Labor Cost = (25 × 8 × 5 × 10) + 500
Labor Cost = 10,000 + 500 = $10,500
The total labor cost for this project is $10,500.